Project Type
Construction
Project Status
Current
Project Category
Water
Project Area
Central SaanichEstimated Cost
$9,800,000
Estimated Timeline
3 years
Contracted To / Performed By
Jacobs Consultancy Canada (design)
Work is planned to replace approximately 1.9km of 762mm concrete pipe on Water Supply Main 4, from the Intersection of Central Saanich Road and Mount Newton Cross Road to the crossing of Highway 17.
The CRD secured a $6-million grant through the UBCM Strategic Priorities Fund to assist with this project.