Magic Lake Estates Wastewater System Infrastructure Replacement Project

Project Type
Construction
Project Status
Completed
Project Category
Stormwater & Wastewater
Project Area
Southern Gulf Islands
Estimated Cost
$9,379,909
Estimated Timeline
01-May-2023 to 31- Dec-2024 (17 months)
Contracted To / Performed By
McElhanney Ltd. (Consulting Engineer), Coast Utility Contracting Ltd.

Background

The Magic Lake Estates (MLE) Sewer Service upgrade works have been underway over the last few years to address the issues facing the aging and failing infrastructure. Condition of the MLE wastewater infrastructure has been documented in past reports and presented at several public open houses held on November 22, 2014, June 6, 2015, February 27, 2016, and April 27, 2019.

Project Funding

Funding for this project is provided by the Green Infrastructure - Investing In Canada Grant Program and Magic Lake Estates Sewer Service.

Project Description

The construction phase of the MLE project will begin in May of 2023. The project includes the decommissioning of the Cannon wastewater treatment plant (WWTP) which will be replaced with a pump station to divert flows for treatment at Schooner WWTP. Schooner WWTP will be upgraded to treat the additional flows from Cannon pump station which includes replacement of other equipment to improve the health, safety, and overall reliability of the facility. At Galleon and Schooner pump stations, the mechanical and electrical components will be replaced, and the remaining pump stations will receive new communication infrastructure.

Future upgrades will focus work at the following facilities:

  • Masthead Pump Station
  • Cutlass Pump Station
  • Buccaneer Pump Station
  • Capstan Pump Station

Magic Lake Estates Wetland Restoration Project

As a result of having to remove some wetlands to complete the wastewater treatment plant project, the CRD will be creating a new wetland area in the adjacent Buck Lake vicinity. The wetland restoration work will begin in the Summer of 2024. For more information about this project, please refer to the Magic Lake Estates Wetland Restoration Project located in our additional information section.

Project Schedule

Next stepApprox. timeline
Mobilize contractor to siteMay 2023
Construction periodMay 2023 to December 2024
Wetland Restoration ProjectSeptember 2024 to November 2024
Test and commission facilitiesSeptember 2024 to October 2024
Warranty reviewAugust 2025
Was this page helpful?

Feedback details

You will NOT receive a reply because this form is anonymous. To get an answer to a question, email us at webdesk@crd.bc.ca

Last Updated: